摘要
2018年11月竣工投产的处理能力为12.0 Mt/a的特大型炼焦煤选煤厂——潘集选煤厂,由于做好了周密又慎重的决策,精心设计,采用了完善的煤泥水处理工艺流程,选用了性能良好的设备,加上操作工人的良好素质和丰富经验,投产后不久就全面实现了GB/T35051-2018《选煤厂洗水闭路循环等级》中的一级标准。
The Panji Coal Preparation Plant,a large-scale coking coal preparation plant with a processing capacity of 12.0 Mt/a,was completed and put into operation in November 2018.Due to thorough and careful decision-making,carefully design,perfect process for slurry treatment,good performance equipment,the good quality and rich experience of operators,soon after the production operation,the closed wash water circuit as the first-grade is fully realized according to the standard of GB/T35051-2018 Grade for closed process water circuit in coal preparation plant.
作者
王恩生
李勇
苑金朝
程翔锐
吴大为
殷志杰
WANG En-sheng(Panji Coal Preparation Plant,Coal Preparation Branch of Huainan Mining Industry(Group)Co.,Ltd,Huainan,Anhui 232082,China)
出处
《煤炭加工与综合利用》
CAS
2019年第10期1-4,I0001,共5页
Coal Processing & Comprehensive Utilization
关键词
选煤厂
煤泥水处理
洗水闭路循环
洗水浓度
单位补充水量
coal preparation plant
slurry treatment
closed wash water circuit
wash water concentration
unit make up water volume
作者简介
王恩生(1982-),男,安徽淮南人,2006年毕业于黑龙江科技学院矿物加工工程专业,工学学士,淮南矿业集团选煤分公司潘集选煤厂总工程师。