白鹤滩水电站工程混凝土预冷措施 被引量:2

Concrete precooling measure for Baihetan Hydropower Station Project
在线阅读 下载PDF
导出
摘要 以白鹤滩水电站工程预冷混凝土生产过程为例,针对混凝土的出机口温度控制在14℃、7℃或更低的设计要求,从混凝土原材料温控和拌制过程温控两方面,提出了"一次风冷+拌和楼风冷+加冰+冷水"的工艺调整措施,达到了混凝土温度控制的设计要求。 By taking the production process of the precooled concrete for the construction of Baihetan Hydropower Station as the actual case,the measure of the technological adjustment,i. e. primary air-cooling + concrete bathing and mixing plant + ice +cold water,is put forward from the aspects of the temperature control of concrete raw materials and the temperature control of the mixing process for the design requirement of that the concrete temperature at the mixer outlet must be controlled at 14 ℃,7 ℃or more lower,which reaches the design requirement of the concrete temperature control.
作者 王延
出处 《水利水电技术》 CSCD 北大核心 2017年第S2期101-103,共3页 Water Resources and Hydropower Engineering
关键词 白鹤滩水电站工程 混凝土预冷 工艺措施 Baihetan Hydropower Station precooling of concrete technological measure
  • 相关文献

同被引文献15

引证文献2

二级引证文献2

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部