文中以洛阳国际会议展览中心为例,对“跳仓法”在该项目中应用的可行性进行分析,深入探析了超长大体积混凝土结构跳仓法施工技术。实践证实,跳仓法在超长混凝土结构施工中能保证混凝土浇筑质量,缩短工期,科学可行。
Taking Luoyang International Convention and Exhibition Center as an example,this paper analyzes the feasibility of the application of"bin hopping method"in this project,and deeply explores the construction technology of the bin hopping method of super long and large volume concrete structure.Practice has proved that the jumping bin method can guarantee the quality of concrete pouring and shorten the construction period significantly in the construction of super long concrete structure.
作者
刘展鹏
朱海瑞
纪晓宇
Liu Zhanpeng;Zhu Hairui;Ji Xiaoyu(Beijing Construction Industrial Construction Investment Development Co.Ltd.,Beijing 100000)
出处
《江西建材》
2023年第4期231-232,235,共3页
Jiangxi Building Materials
关键词
洛阳国际会议展览中心
超长混凝土结构
跳仓法
施工技术
Luoyang International Convention and Exhibition Center
Ultra-long concrete structure
Vault jumping method
Construction technology
作者简介
刘展鹏(1992-),男,山东莱西人,专科,助理工程师,主要研究方向为建筑施工;通信作者:纪晓宇(1991-),男,河北廊坊人,专科,助理工程师,主要研究方向为建筑施工。