摘要
巴塘水电站导流洞渐变段顶拱受不良地质条件的影响出现了塌方,由于工期紧,若采用传统平面大模板浇筑边墙的方式其施工工期不能够满足导流目标要求。阐述了该工程应用钢模台车成功地完成导流洞进口渐变段边墙混凝土衬砌施工的过程,较平面大模板节约工期6 d,其混凝土外观质量优于平面大模板衬砌渐变段边墙混凝土,不仅节约了施工成本,而且为灌浆争取了时间,所取得的经验可为类似工程借鉴。
The top arch of the transition section of the diversion tunnel of Batang Hydropower Station collapsed due to the adverse geological condition.Due to the tight construction schedule,the diversion target couldn't be complete if the traditional flat large formwork to pour the side wall were used.This paper expounds that the concrete lining construction of the side wall of the inlet transition section of the diversion tunnel in this project was successfully completed,and 6 days were saved compared with the flat large formwork lining plan.The appearance and quality of the concrete is better than the flat large formwork plan.The application of steelshuttering trolley not only saves the construction cost,but also saves the time for the grouting.The obtained experience can provide reference for similar projects.
作者
张显为
丁善锋
刘文明
ZHANG Xianwei;DING Shanfeng;LIU Wenming(Sinohydro Bureau 5 Co.,Ltd.,Chengdu Sichuan 610066)
出处
《四川水力发电》
2023年第3期40-43,共4页
Sichuan Hydropower
关键词
巴塘水电站
钢模台车
渐变段
衬砌混凝土
Batang Hydropower Station
steel-shuttering trolley
transition section
lining concrete
作者简介
张显为(1987-),男,甘肃定西人,项目安全总监,工程师,从事水利水电工程施工技术与安全管理工作;丁善锋(1980-)男,河南濮阳人,项目总工程师,高级工程师,从事水利水电工程施工技术与管理工作.刘文明(1981-)男,甘肃陇南人,项目副经理,工程师,从事水利水电工程施工技术与管理工作.