为简化自然通风空冷塔X型支柱的施工工艺,缩短施工时间,降低施工成本,研究钢管混凝土X支柱自然通风空冷塔技术,并应用于陕西某煤电一体化电厂项目。工程实践表明:采用钢管混凝土X支柱空冷塔新技术后,可大幅缩短斜支柱的施工工期,提高作业效率,减少人工投入,降低工程造价,具有显著的经济效益和社会效益。
In order to simplify the construction process of the diagonal columns of natural draught dry cooling tower(NDDCT),shorten the construction time and reduce the construction cost,this paper studied the technology of the new type concrete-filled steel tube X-shaped diagonal for NDDCT and applied it to a coal power integrated power plant project in Shaanxi.The engineering application practice shows that NDDCT with new type concrete-filled steel tube X-shaped diagonal column can greatly shorten the construction period of columns,reduce labor input,improve build efficiency and reduce construction cost,which has remarkable economic and social benefits.
作者
石天琪
闫杰
张宏飞
侯宪安
吕兰
SHI Tianqi;YAN Jie;ZHANG Hongfei;HOU Xianan;LYU Lan(Yanghuopan Coal Power Co.,Ltd.of Shaanxi Yulin Energy Group,Yulin 719316,China;Northwest Electric Power Design Institute Co.,Ltd.of China Power Engineering Consulting Group,Xi'an 710075,China)
出处
《电力勘测设计》
2022年第6期20-25,共6页
Electric Power Survey & Design
关键词
自然通风空冷塔
钢管混凝土X支柱
加强型X节点
泵送顶升法
natural draught dry cooling tower(NDDCT)
concrete-filled steel tube X-shaped diagonal column
reinforced cross joint of X-shaped concrete-filled steel tube column
pumping-up casting method
作者简介
第一作者:石天琪(1973-),男,高级工程师,从事大型火力发电厂项目建设管理相关工作。