BIM技术辅助盾构区间下穿既有高架桥的施工技术研究——以天津地铁11号线一期工程为例 被引量:4

Research on Construction Technology of Shield Tunneling under Existing Viaduct Based on BIM Technology
在线阅读 下载PDF
导出
摘要 目前,我国城市地铁网络分布已趋越来越密集的趋势,地铁线路与既有建筑桩基础交叉问题日显突出。以天津地铁11号线一期工程为工程背景,利用BIM技术建立的空间模型,对施工交叉空间进行动态模拟,可精确分析地铁盾构与建筑桩基础交叉的三维空间问题,为地铁区间下穿高架桥提供技术指导。应用并推广了BIM技术,响应了我国技术政策方针。 Earth pressure balance shield tunneling machine is widely used in subway tunnel construction because of its adaptability to various ground conditions,higher construction efficiency and safer working environment.With the distribution of urban subway network becoming more and more dense,it will inevitably lead to the crossing problem between subway lines and existing viaduct pile foundation.Based on the first phase of Tianjin Metro Line 11 project as the engineering background,this paper uses BIM technology to establish a space model,and carries out strict management and dynamic simulation of construction space,so as to maximize the use of construction space and avoid unnecessary accidents and losses.It provides guidance for the application of shield tunneling method in underground viaduct.
作者 王松涛 李星 丁杰 WANG Songtao;LI Xing;DING Jie(General-contract Engineering Branch of cccc Third Highway Engineering Co.LTD.,Beijing 100023)
出处 《福建建筑》 2021年第7期128-131,共4页 Fujian Architecture & Construction
关键词 BIM 土压平衡盾构 地铁隧道 施工技术 沉降控制 BIM Earth pressure balance shield Subway tunnel Construction technology Settlement control
作者简介 王松涛(1987-),男,工程师。E-mail:383314559@qq.com。
  • 相关文献

参考文献7

二级参考文献38

共引文献72

同被引文献25

引证文献4

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部