摘要
为充分利用需求响应资源,可对不同需求响应资源进行整合。本文以调度成本最低为目标函数,构建了含直接负荷控制和可中断负荷的优化模型。对比了直接负荷控制及可中断负荷在受控量、受控时间、补偿价格等方面的异同,重点分析了两者在负荷反弹方面的差异。采用机会约束考虑了负荷预测的不确定性,并将机会约束转化为其确定性等价形式。采用拉格朗日松弛法对确定性模型求解,并采用蒙特卡罗模拟对机会约束置信水平进行验证。算例表明模型综合了直接负荷控制移峰和可中断负荷削峰特点,可有效降低系统高峰时段负荷,避免二次负荷高峰的产生。
Different kinds of demand response resources can be integrated together to make full use of them.The optimal dispatch model that contains direct load control (DLC)and interruptible load (IL)is proposed to minimize the schedu-ling cost.The differences or similarities among controlled a-mount,controlled duration and compensation price are com-pared,especially the difference in energy payback of DLC and IL.Chance constraint is used to handle the uncertainties in load forecasting,and the chance constraint is converted into its deterministic equivalent form.In addition,the la-grangian relaxation method is used to solve the deterministic model,and the preset confidence level is verified through Monte Carlo simulation.The model that integrates the peak removing characteristic of DLC and peak clipping character-istic of IL can effectively reduce the load peak and eliminate the second peak load.
作者
艾欣
周树鹏
赵阅群
唐亮
AI Xin ZHOU Shupeng ZHAO Yuequn TANG Liang(State Key Laboratory of Alternate Electrical Power System with Renewable Energy Sources (North China Electric Power University), Beijing 102206, China State Grid Anhui Electric Power Company, Hefei 230022, China)
出处
《现代电力》
北大核心
2016年第6期1-6,共6页
Modern Electric Power
基金
国家高技术研究发展计划项目(863计划)(2015AA050102)
国家自然科学基金项目(513111122)
关键词
机会约束规划
可中断负荷
直接负荷控制
需求响应
优化调度
chance constrained programming
interruptibleload (IL)
direct load control (DLC)
demand response(DR)
optimal dispatch
作者简介
艾欣(1964-),男,教授,博士生导师,研究方向为电力系统分析与控制、新能源发电与智能电网,E-mail:aixin@ncepu.edu.cn;
周树鹏(1988-),男,博士研究生,研究方向为电力系统分析与控制,E-mail:627545060@qq.com;
赵阅群(1987-),男,博士研究生,研究方向为电力系统分析与控制,E-mail:313581345@qq.com;
唐亮(1982-),男,硕士研究生,研究方向为新能源电力系统及微网,E-mail:tang10311@ah.sgcc.com.cn。