介绍了我国太阳能发电开发规划、布局特点及存在的问题;基于建立的光伏发电出力特性指标,分析了大规模光伏发电并网对电力系统规划提出的新要求;提出了太阳能发电消纳研究方法,根据"十二·五"期间西北地区太阳能发电规划目标,分析了西北电网太阳能消纳能力,2015年,西北地区太阳能发电装机规模为1 320万kW,电网调峰能力不能满足光伏、风电等新能源消纳需求,需要跨区平衡消纳。
The planning, layout characteristics and existing problems of solar power development in China are introduced. Based on the output characteristic index of PV generations, the new requirements of large-scale PV power integration is analyzed on the power system planning, and the analytical method of solar power accommodation is proposed. According to the planning targets of solar power generation of the “12th Five-Year Plan” period in the northwestern region, the solar power accommodation capacity of the northwest grid is studied. It is predicted that by the year of 2015, the installed solar power capacity in the northwestern region will reach 13.2 GW, and the balancing capability of the local power grid can' t meet the accommodation requirement of such new energies as PV and wind power. Trans-region balance is therefore needed for accommodation of new energy.
出处
《中国电力》
CSCD
北大核心
2013年第1期1-6,共6页
Electric Power
关键词
电力规划
太阳能发电
布局
消纳
power planning
solar power generation
layout
accommodation
作者简介
胡泊(1979-),男,湖南衡阳人,博士,主要从事能源与电力发展战略、规划及能源技术经济等方面的研究。E-mail:hubo@sgeri.sgcc.com.cn