本文对珠江电厂300MW机组密封油系统所存在的问题进行了分析,提出了合理的改进措施。其关于增装氢侧加压排油管的经验可供同型机组处理氢侧油箱满油及发电机进油缺陷时参考。
Based on the analysis of operation problems in sealing oil system of a 3OOMW generator, zhujiang power plant. this paper puts forward some applicable improvements, of which the practice of supplementary pressured oi1 returll pipe for generator hydrogen side can be used as reference for similar generators experiencing the overflow from the oil tank in generator hydrogen sealing system.
出处
《热力发电》
CAS
北大核心
1997年第1期46-48,共3页
Thermal Power Generation