隔河岩枢纽水力学原型观测及检查成果 被引量:3

Prototype observation and inspection of Geheyan Project
在线阅读 下载PDF
导出
摘要 2002年对隔河岩枢纽进行了水力学原型观测,内容包括流态、流速、脉动压力等,并取得了成果。1998年枢纽经历大洪水的考验,随后进行抽水检查,发现消力池底板有冲蚀磨损,1999年进行修复处理。2002年泄洪后检查未发现损坏现象。这说明联合消能工效果是显著的,工程质量还是好的,模型试验与原型观测成果基本一致。 In 2002,hydraulics prototype survey was carried out in Geheyan Project, contents included flow pattern,velocity and pulsating pressure etc.. In 1998, the project operated under great flood condition and subsequently dewatered inspection indicated that some erosion and abrasion existed on the bottom board of plunge pool. In 1999,repair treatment was made on damaged section. After 2002 flood, by inspecting again no damage was found. This indicated that unified energy dissipators effect was distinct and constuction quality was good. Model test data are consistent with prototype survey.
出处 《长江科学院院报》 CSCD 北大核心 2003年第5期18-20,共3页 Journal of Changjiang River Scientific Research Institute
关键词 宽尾墩 窄缝挑坎 水垫塘 联合消能工 拱坝泄洪 flaring gate pier narrow-slot bucket plunge pool unified energy dissipator flood discharge of arch dam
作者简介 高仪生(1943一),男,湖南风凰人,长江科学院水工研究所高级工程师,主要从事水工水力学研究
  • 相关文献

参考文献10

  • 1王才欢.1998清江隔河岩工程水力原型观测研究报告[R].武汉:长江科学院,1999..
  • 2高仪生.清江隔河岩水利枢纽收缩射流水垫塘联合消能工1/58整体模型试验报告[R].武汉:长江科学院,1993..
  • 3高仪生 金宝芬.隔河岩枢纽泄洪消能试验研究[R].武汉:长江科学院,1993..
  • 4陈元清 王伟民.清江隔河岩水利枢纽消力池水力学原型观测报告[R].武汉:长江科学院,1992..
  • 5高仪生 汪世鹏.清江隔河岩2002年汛期原型观测试验报告[R].武汉:长江科学院,2003..
  • 6高仪生 金宝芬.隔河岩枢纽泄洪消能试验研究[R].武汉:长江科学院,1993..
  • 7高仪生.清江隔河岩水利枢纽收缩射流水垫塘联合消能工1/58整体模型试验报告[R].武汉:长江科学院,1993..
  • 8陈元清 王伟民.清江隔河岩水利枢纽消力池水力学原型观测报告[R].武汉:长江科学院,1992..
  • 9王才欢.1998清江隔河岩工程水力原型观测研究报告[R].武汉:长江科学院,1999..
  • 10高仪生 汪世鹏.清江隔河岩2002年汛期原型观测试验报告[R].武汉:长江科学院,2003..

同被引文献19

引证文献3

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部