期刊文献+

一种可调节式倒三角桁架拼装措施 被引量:1

An Assembling Method of Adjustable Inverted Triangle Truss
在线阅读 下载PDF
导出
摘要 机场、交通枢纽等钢结构工程中大型倒三角桁架和网架结构的拼装使用不可调节拼装措施,对标高不同的构件进行定位时胎架需要重新布点和组装,大大降低施工效率;施工中用一种可调节式倒三角桁架拼装措施,有效地改善了以上问题,通过在国内西南某奥林匹克体育中心建设过程中的实践应用,证明拼装用可调节式倒三角桁架拼装措施解决了现有不可调节拼装胎架存在的标高调节繁琐、重复布置点位、偏差调节困难等缺点。 In the steel structure construction project such as airport terminals and waiting halls of transportation junction,large-scale inverted triangular space trusses and grid structures are assembled using fixed assembly jigs. When assembly levels of structural members are different,the need for re-assembly of the jigs will greatly reduce the construction efficiency. The use of the adjustable inverted triangular trussed assembly jig in the construction can effectively address the abovementioned issue. Through the practical application in the construction project of an Olympic Sports Center in Southwest China,it is proved that the adjustable inverted triangular trussed assembly jig can perfectly solve the existing problems of the fixed assembly jig,e. g. the cumbersome adjustment of the elevation,repeated setting-out surveys,the difficulty of adjusting deviation.
出处 《施工技术》 CAS 北大核心 2017年第S2期1269-1271,共3页 Construction Technology
关键词 钢结构 桁架 拼装 可调节式倒三角桁架 steel structures trusses assembly adjustable inverted triangular truss
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部