摘要
澳门新濠天地项目由于处在澳门氹仔大型商业区,其中有正在运营的多家五星级酒店以及各类品牌零售店。施工过程需要将对现有的建筑以及商业的影响降至最低,这就给施工方案的选择以及质量的控制带来了极大的难度。结合工程的实际情况,通过合理的施工安排以及对桩基以及拆除等关键施工工艺的严格控制,保证了整个工程的顺利进行,并且有效地保证了工程的进度和质量。
A project in Macao is located in large business zone,which includes five-star hotels and brand monopolized shops. During the construction,we need to minimize the impact on the existing building and business,which brings great difficulty to the choice of construction scheme and quality control. According to the actual situation of the project,we arranged smooth progress of the whole project,and effectively ensure the progress and quality of the project,through the reasonable construction arrangement,as well as the strict quality control of pile piles and removal works.
出处
《施工技术》
CAS
北大核心
2015年第S2期95-97,共3页
Construction Technology
关键词
扩展工程
桩基
拆除
质量控制
expansion project
files
demolition
quality control