某在建工程部分剪力墙混凝土置换施工方案设计 被引量:11

DISCUSSION OF CONSTRUCTION SCHEME OF REPLACEMENT CONCRETE OF A PART OF SHEAR WALLS OF AN UNDER CONSTRUCTION PROJECT
在线阅读 下载PDF
导出
摘要 某在建框筒结构部分剪力墙强度不足,对比了几种常用的加固方法,最适合本工程的加固方法为混凝土置换法;根据工程实际情况提出了混凝土置换施工的难点;计算出了需置换混凝土的剪力墙的竖向力,提出了用槽钢形成格构式支撑的方式进行支撑,并根据各墙肢所受竖向力及格构支撑的承载力,计算出了各墙肢所需支撑数量。 The strength of a part of shear walls of an under construction frame-tube structure residence was insufficient,several common reinforcement methods have been compared,the most suitable strengthening method for this project was concrete displacement;According to the actual situation of the project,the difficult points have been presented;The vertical force of the shear walls which need to replace concrete has been worked out,the way with channel steel to form latticed steel-structural brace to support has been presented,and according to the vertical force of the shear walls and the bearing capacity of the latticed steel—structural brace,the number of the braces of each wall has been worked out.
作者 余兴华 吕林
出处 《建筑技术开发》 2014年第8期63-66,共4页 Building Technology Development
关键词 框筒结构 剪力墙 混凝土置换 frame-tube structure shear wall replacement concrete
  • 相关文献

参考文献4

二级参考文献8

共引文献132

同被引文献41

引证文献11

二级引证文献37

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部