摘要
在西藏水电开发迎来大发展之际,需妥善解决好较大规模的移民搬迁安置问题。对此,以西藏忠玉水电站工程为例,从区域特点、居民点选址、总体规划布局、场平工程设计、交通工程设计、供水工程设计、居住空间规划设计、公共服务设施规划、景观绿化工程设计等方面,阐述移民居民点规划设计要点,可为今后类似工程移民安置提供参考和借鉴。
As the hydropower development in Tibet enters a period of rapid growth,it is essential to properly address the large-scale issue of resettlement.Taking the ZY Hydropower Station project in Tibet as a case study,this paper discusses key aspects of resettlement community planning and design,including regional characteristics,site selection for residential areas,overall planning and layout,land leveling design,transportation infrastructure,water supply engineering,residential space planning,public service facility planning,and landscape greening design.The paper aims to provide valuable references and insights for the resettlement planning of similar hydropower projects in the future.
作者
胡斌
HU Bin(Northwest Engineering Co.,Ltd.,Xi’an 710065,China)
出处
《广东水利电力职业技术学院学报》
2025年第1期61-64,共4页
Journal of Guangdong Polytechnic of Water Resources and Electric Engineering
关键词
西藏
水电站工程
移民
居民点
规划设计
Tibet
hydropower project
migrants
residential areas
planning and design
作者简介
胡斌,男,高级工程师,主要从事水利水电工程建设征地移民安置规划设计工作。