摘要
大黑汀水库坝基静力水准系统安装运行近20年,运行过程中,测点测值出现异常。通过监测系统测试、现场和监测资料检查、人工观测资料对比分析,对运行过程中存在的异常情况进行全面分析研究,查找静力水准系统运行异常原因,判定坝基垂直位移正常,坝体运行稳定,可供类似工程借鉴。
The static leveling system for dam foundation of Daheiting reservoir has been in operation for nearly 20 years.During operation,abnormal values were detected at measuring points.Through the mon-itoring system test,on-site and monitoring data inspection,and manual observation data comparison and analysis,comprehensive analysis and study of the abnormal conditions existing in operation are con-ducted to find out the cause reasons,and it is determined that the vertical displacement of dam founda-tion is normal and the dam body is operating stably,which can be used for reference to similar projects.
作者
赵利锋
ZHAO Lifeng(Luan River Diversion Project Management Bureau,Haihe River Water Conser-vancy Commission,MWR)
出处
《大坝与安全》
2024年第6期34-40,共7页
Dam & Safety
关键词
工程监测
自动化
静力水准系统
运行异常
资料分析
engineering monitoring
automation
static leveling system
abnormal operation
data analysis
作者简介
赵利锋(1981-),男,河北唐山人,高级工程师,主要从事大坝安全监测工作。作者邮箱:zhaolifeng1@126.com。