摘要
针对碾盘山水利枢纽工程采用BIM设计,泄水闸的桩基设计具有数量大、桩长不一、工程量难以准确统计,采用传统二维和三维设计进行桩基布置,工作流程繁琐且耗时耗力。基于Dynamo的参数化和模块化功能探索大量桩基的快速布置,实现了大批量桩基的快速建模、出图和工程量统计,减少了人为计算的误差,极大地提高了统计精度,使设计效率与质量显著提升。
BIM design is conducted in Nianpanshan Water Conservancy Project.Due to the large quantity,varying pile lengths,and difficulty in engineering quantity calculation in the design of the pile foundation of sluice gates,traditional two-dimensional and three-dimensional pile foundation design and arrangement is complicated and time-consuming.Based on the parameterized and modularized design functions in Dynamo,rapid arrangement of a large number of foundation piles is explored.It achieves the rapid modeling,drawing and engineering quantity statistics of a large number of piles,which greatly reduces the human calculation errors and improves the statistical accuracy,leading to significant improvements in design efficiency and accuracy.
作者
陈慧敏
王梦雅
汪洋
年夫喜
CHEN Huimin;WANG Mengya;WANG Yang;NIAN Fuxi(Hubei Institute of Water Resources Survey and Design Co.,Ltd.,Wuhan 430070,China)
出处
《水电与新能源》
2024年第9期48-51,55,共5页
Hydropower and New Energy
作者简介
陈慧敏,女,工程师,主要从事水工设计方面的工作。