摘要 凌庄水厂升级改造一期工程总规模为30×10^(4)m^(3)/d,净水工艺采用预臭氧接触池-机械混合池-上向流炭吸附脉冲澄清池-压力超滤系统,出厂水采用氯胺消毒。运行半年期间,脉冲澄清池上升流速为2.6~5.2 m/s,超滤运行膜通量为39.4 L(m^(2)·h),跨膜压差维持在25~85kPa之间。项目整体运行自动化程度高,系统出水水质稳定,浊度均在0.1 NTU以下,为超滤在国内大型水厂的应用提供了示范作用。 The first phase of Lingzhuang Waterworks upgrading project has a scale of 30×10^(4)m^(3)/d,adopting the treatment process of ozonation contact reactor+mechanical mixing tank+upflow carbonadsorption pulse clarifier+pressure ultrafiltration(UF),and the treated water was disinfected bychloramine.During the half-year operation,the rising velocity of the pulse clarifier was 2.6~5.2 m/s,the UF membrane flux was 39.4 L(m^(2)-h),and the trans-membrane pressure difference(TMP)wasmaintained at 25~85 kPa.The overall operation of the project was highly automated,had stable qualityof the system effluent and turbidity below 0.1 NTU,which provided a demonstration for the application ofUF membrane in large domestic waterworks.
作者 马骏 段方旭 袁野 杨扬 Ma Jun;Duan Fangxu;Yuan Ye;Yang Yang(Tianjin Waterworks Group Co.Lad.,Tianjin 300040,China;Lingzhuang Waterworhs,Tianjin Waterworks Group Co.Ltd.,Tianjin 300381,China)
出处 《供水技术》 2021年第2期32-36,共5页 Water Technology
关键词 上向流 炭吸附澄清池 压力超滤膜 氯胺 消毒 第三代净水厂 upflow carbon adsorption clarifier pressure UF membrane chloramine disinfection the third generation waterworks
作者简介 马骏(1971-),男,天津人,本科,主要从事工程项目建设管理工作。E-mail:zlsabb@163.com。
  • 相关文献

参考文献3

二级参考文献20

共引文献74

同被引文献19

引证文献4

二级引证文献16

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部