雅万高铁大直径盾构隧道下穿轻轨施工技术 被引量:4

Construction Technology of Large-diameter Shield Tunnel Underpassing Light Rail of Jakarta-Bandung High-speed Railway
在线阅读 下载PDF
导出
摘要 以印度尼西亚雅万高铁1号隧道施工项目为依托,研究复杂地层大直径盾构隧道下穿轻轨施工技术。采用我国自主研发的大直径泥水加压平衡盾构机,在分析场地工程地质条件的基础上,开展盾构性能参数研究、始发盾构掘进技术研究和盾构正常掘进研究。该施工技术方案解决高烈度地震地区地层复杂环境下高铁盾构掘进施工问题,盾构掘进风险得到有效控制。 Relying on the construction project of No.1 Tunnel of Jakarta\|Bandung High\|speed Railway in Indonesia,in order to study the related construction technology scheme of large-diameter shield tunnel underpassing light rail in complex stratum,the large-diameter muddy water pressure balancing shield machine independently developed by China is used to research on shield performance parameters,initial shield tunneling technology and normal shield tunneling on the basis of engineering geological conditions.It solves the problem of high-speed railway shield tunneling construction in complex stratum environment in high-intensity earthquake areas,and the shield tunneling risk is effectively controlled.
作者 苗壮 MIAO Zhuang(China Railway Design Group Co.,Ltd.,Tianjin 300308,China)
出处 《施工技术》 CAS 2020年第16期92-94,127,共4页 Construction Technology
基金 中国铁设集团公司课题:高烈度震区火山胶结地层复杂环境下高铁盾构隧道设计施工关键技术研究(2020YY340629)。
关键词 地下工程 高速铁路 隧道 盾构 下穿轻轨 施工技术 undorground engineering high speed rail tunnels shields underpass light rail construction
作者简介 苗壮,工程师,E-mail:sdsmiaozhuang@126.com。
  • 相关文献

参考文献4

二级参考文献22

共引文献56

同被引文献37

引证文献4

二级引证文献7

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部