摘要
在应用现代科技建设公路工程中,对于复杂的工程,采用施工设计一体化和计算机技术,将施工阶段中的各种信息建成模型,根据模型推断,可解决设计方案的不足和施工中存在的问题。本文以G310线临夏至大河家公路滑坡处治工程中的关键工程抗滑桩的选用,就实际工程建设中施工设计一体化技术应用展开探讨。
In the application of modern science and technology in the construction of highway engineering, for complex projects, the integration of construction design and computer technology as well as computer are used to build the model of various information in the construction stage. According to the model inference, the shortage of design scheme and the problems in construction can be solved. Based on the selection of anti-slide pile in the landslide treatment project of Linxia-Dahejia highway on G310, this paper discusses the application of construction design integration technology in actual engineering construction.
出处
《中国建材科技》
2020年第4期136-138,共3页
China Building Materials Science & Technology
关键词
滑坡
施工设计一体化
landslide
integration of construction and design