为解决某医院项目黏滞阻尼器支架单件构件质量较大、预埋钢板厚度较厚等导致的吊装困难问题,将1套阻尼器支架拆分为3块后在施工现场重新组装成整体,使得吊装难度大大降低。对阻尼器钢构件支架的制作、预埋件的预埋、阻尼器吊装孔的预埋、支架的安装、阻尼器的安装等内容进行了详细叙述,以期为类似工程提供参考。
To solve the hoisting difficulties caused by the large mass of single component and thick embedded steel plate of the viscous damper support in a hospital project, the hoisting difficulty is greatly reduced by dividing one set of damper support into three pieces and reassembling them in the construction site. The production of the steel support, the embedment of the embedded parts, the embedment of the damper hoisting hole, the support installation and the damper installation are described in detail in order to provide reference for similar projects.
作者
于峰
潘传洲
肖婷
YU Feng;PAN Chuanzhou;XIAO Ting(Zhongtian Construction Group Co.,Ltd.,Hangzhou,Zhejiang 310008,China)
出处
《建筑施工》
2020年第3期342-344,共3页
Building Construction
关键词
黏滞阻尼器
预埋钢板
散件吊装
分段分层焊接
viscous damper
embedded steel plate
bulk lifting
segmented and layered welding
作者简介
于峰(1988-),男,本科,高级工程师。通信地址:浙江省杭州市之江路438号中天商务楼4楼技术处(310008)。电子邮箱:240118161@qq.com。