山西煤炭运销集团华阳煤业K2灰岩水防治

Prevention and Control of K2 Limestone Water in Huayang Coal Industry of Shanxi Coal Transportation and Sales Group
在线阅读 下载PDF
导出
摘要 针对华阳煤业总回风大巷和15煤运输巷钻孔长期出水,且出水量长期稳定在1200m3/d的情况,从减少矿方排水费用和保障安全生产的角度出发,根据相关规定,结合矿方实际需求,采用K2灰岩注浆办法,封堵水源通道,从而达到减少排水费用、保障矿井安全生产的目的。 There is a long-term water flow of Huayang Coal Industry's total return-air roadway and the 15 coal transportation lane,and the water yield is stable at 1200m3/d for a long time.In order to reduce the mine drainage costs and ensure safe production,according to relevant regulations and the practical demand of the mine,we adopt K2 limestone grouting method,blocking water channel,to lessen the cost of drainage,and achieve the purpose of mine safety production.
作者 李雁川 Li Yan-chuan(Technology Institute of Shanxi Jincheng Anthracite Coal Mining Group Co.,Ltd.,Shanxi Jincheng 048006)
出处 《山东煤炭科技》 2019年第12期149-151,共3页 Shandong Coal Science and Technology
关键词 水患分析 水害防治 K2灰岩岩溶水 flood analysis flood control K2 limestone water
作者简介 李雁川(1990-),男,山西晋城人,汉族,本科,2013年毕业于中国矿业大学(徐州)电子信息科学与技术专业,助理工程师,现主要从事矿井物探、矿井地质与水文地质相关研究工作。