通过工程实例,对55mT梁在运输过程中容易出现的技术问题进行分析,并对55mT梁在梁场起吊、运输过程加强控制,通过受力分析,确保55mT梁在运输过程中的安全,并架设完成。在施工中,总结梁体在运输、架设过程中需控制的施工工艺及相关技术措施,为类似施工提供借鉴。
The technical problems that the 55 mT beam is easy to appear during the transportation process are analyzed through the project example, and the control of the 55 mT beam in the beam field is strengthened. Through the force analysis, the safety of the 55 mT beam in the transportation process is ensured, and the erection is completed. In the construction, the construction technology and related technical measures to be controlled during the transportation and erection of the beam body are summarized, and the reference for similar construction is provided.