摘要
为了解决恒源煤业151303综掘巷道原通风方式下掘进迎头粉尘浓度过高的问题,拟采用抽、压组合的通风系统来降低迎头煤尘浓度,并进对风筒的布置参数进行研究。通过研究发现:压风筒筒口距离掘进迎头13m时,抽风筒固定于综掘机距迎头4m的位置处的除尘效果最佳。现场实测发现在采取了合理的综合降尘措施后,掘进工作面煤尘浓度下降了约89%,可以满足正常安全的掘进此巷道。
In order to solve the problem of excessive dust concentration in the original ventilation mode of the 151303 comprehensive roadway of Hengyuan Coal Mine, it is proposed to use the combined ventilation and pressure system to reduce the concentration of coal dust in the head, and to study the layout parameters of the air duct. Through research, it is found that when the pressure cylinder mouth is 13m away from the heading, the dust extraction cylinder is fixed at the position where the comprehensive excavator is 4m away from the head, and the dust removal effect is best. On-site measurement found that after taking reasonable comprehensive dust reduction measures, the coal dust concentra tion in the heading face decreased by about 89%, which can meet the normal and safe tunneling.
作者
王登峰
WANG Dengfeng(Jin Coal group Zezhou Hengyuan Coal Industry Co., Ltd. , Shanxi Jincheng 048000)
出处
《煤矿现代化》
2019年第6期110-112,115,共4页
Coal Mine Modernization
关键词
综掘
降尘措施
粉尘浓度
抽、压组合的通风系统
Comprehensive excavation
Dust reduction measures
Dust concentration
Pumping and pressing combination ventilation system
作者简介
王登峰(1988-),男,山西运城人,2009年7月毕业于山西省煤炭职工联合大学通风与安全专业,通风助理工程师,现从事矿井通风技术工作.