双代号网络图绘制是《施工组织》课程的教学重点和难点,在教学过程中充分揭示绘图方法的规律,提高绘图方法的系统性,是减少学生绘图错误的有效途径.本文归纳总结了双代号网络图绘制的规则和绘图步骤,编制了双代号网络图绘制过程流程图,并进行了实例演示,以期为双代号网络图绘制教学提供方法参考.
Double code network drawing is the key and difficult point in the course of construction organization.It is an effective way to reduce the students’drawing errors by fully exposing the law of drawing methods and improving the system of drawing methods.This article summarized the rules of double code network chart drawing and drawing steps,compiled the double code network chart drawing process flow diagram,and a demonstration example,provides a method of double code network chart drawing teaching reference.
作者
杨坦
刘雪莉
战婧
蒋亚龙
李改
YANG Tan;LIU Xue-li;ZHAN Jing;JIANG Ya-long;LI Gai(College of Civil and Environmental Engineering,Anhui Xinhua University,Hefei 230088,China)
出处
《白城师范学院学报》
2018年第10期72-77,共6页
Journal of Baicheng Normal University
基金
安徽省省级质量工程项目(2016zjjh032)
安徽新华学院校级教研重点项目(2017jy002)
安徽新华学院校级教研重点项目(2017jy014)
关键词
双代号网络图
流程图
绘图
double code network diagram
flow chart
drawing
作者简介
杨坦(1987—),男,讲师,硕士,研究方向:系统安全分析和高等教育研究.