空载试运行阶段是城市轨道交通新线投入试运营前的核心阶段,对新线安全稳定地运行起着关键作用。通过对新线空载试运行的组织要求、实施前置条件、总体计划安排、试运行跑图、试运行基本条件评审准备等方面进行分析,提出完整的空载试运行组织思路及优化措施。
No-load test running is the core stage for new lines before trial operation, it plays an important role of safety and stability in new line operation. In this paper, complete organization methods and optimized control meas- ures for no-load running test are put forward, based on an analysis of the organizational requirements, preconditions of operation, overall arrangement, train test running graph, fundamental preparations for the basic conditions of test running evaluation.