摘要
针对红谷隧道一期管节沉放安装施工中产生的轴线偏差问题,介绍管节沉放安装工艺,总结管节沉放安装轴线偏差的影响因素和常用的纠偏方法,分析红谷隧道一期管节沉放安装施工产生轴线偏差的原因,采用横向错位法和摆尾法对一期沉放出现的轴线偏差进行纠偏,一期管节最终的轴线偏差控制在设计允许范围内。从钢端壳制作精度、横向水流和沉放测量精度等方面对二期管节沉放轴线控制提出建议,以期为今后的沉管隧道管节沉放施工提供借鉴。
The sinking and installation technologies for Honggu Tunnel in Nanchang are introduced. The influencing factors of deviation of tunnel segment and deviation rectification methods are summarized. The horizontal dislocation method and segment tail swing method are adopted for deviation rectification of tunnel segment of Phase 1 of Honggu Tunnel. The construction effect is good. Suggestions are given for axial line control of tunnel segment sinking of Phase 2 of Honggu Tunnel in terms of steel end shell manufacturing accuracy, horizontal flow velocity and segment sinking monitoring accuracy.
出处
《隧道建设》
北大核心
2016年第9期1106-1113,共8页
Tunnel Construction
关键词
沉管隧道
管节沉放
管节纠偏
横向错位法
摆尾法
immersed tunnel
tunnel segment sinking
tunnel segment deviation rectification
horizontal dislocationmethod
tail swing method
作者简介
谢震灵(1966-),男,江西樟树人,1998年毕业于中国社会科学院,建设项目管理学专业,硕士,高级工程师,现主要从事给排水、市政道路桥梁、轨道交通、房屋建筑工程专业监理工作。E-mail:956965570@qq.com。