大型建筑工程项目资源配置模型及策略研究——基于系统动力学的建模和仿真 被引量:33

Resource Allocation Model and Strategy Research of Large-scale Construction Project:System Dynamics Modeling and Simulation
原文传递
导出
摘要 大型建筑工程项目多类型资源的有效配置,是现阶段项目管理理论与工程管理实践面临的关键问题,特别是在考虑工艺顺序和间歇时间的工作可操作性特点,以及多资源之间反馈影响的情况下。通过整合挣值法和系统动力学理论,在分析资源可用性和工作可操作性之间因果关系的基础上,本文构建了大型建筑工程项目多资源配置的系统动力学模型。以上海市重大工程投资统计数据作为模型参数依据,模型的仿真结果表明:建筑工程项目不同类型资源其配置重要性与系统影响性存在显著差异,在制定资源配置策略时应同时考虑项目运作方式的特征与多资源之间的匹配,资源不匹配则容易导致资源配置系统失去稳态或策略失效。这为进一步研究项目管理中多资源配置提供了理论参考和实践支持。 The efficient allocation of different types of resources in large-scale construction projects is a key issue that the project management theory and practice facing nowadays.Especially both the work operability,which including the process sequences and time interval,and the feedback impact of these resources are considered.Combining the earned value method and the system dynamics theory,this paper establishes a system dynamics model of multiple resource allocation of large-scale construction projects.The modeling is based on the causal analysis between the resource availability and the work operability.Major investment construction projects statistical data in Shanghai are used to set the model parameters.The simulation results indicate that there is significant difference on the allocation importance and systematically affect of different resources in construction projects.Both the project operation model and multiple resource matching should be considered when resource allocation strategies are developed.Mismatch of resources always result in unsteady of the resource allocation system or strategy failure.This research will provide theoretical reference and practice support to the further research on multiple resource allocation of project management.
出处 《中国管理科学》 CSSCI 北大核心 2016年第3期125-132,共8页 Chinese Journal of Management Science
基金 国家自然科学基金资助项目(71372079)
关键词 资源配置 项目管理 系统动力学 resource allocation project management system dynamics
作者简介 通讯作者简介:仲勇(1976-),男(汉族),江苏东台人,华东理工大学商学院博士研究生,高级工程师,研究方向:项目管理,E—mail:LIB305@126.com.
  • 相关文献

参考文献21

  • 1Vaziri K,Carr P,Nozick L. Project planning for con-struction under uncertainty with limited resources [J],Journal of Construction Engineering and Management,2007,133(4): 268-276.
  • 2丁雪枫,尤建新.多模式资源受限项目调度问题的混合优化算法研究[J].中国管理科学,2012,20(S1):154-159. 被引量:16
  • 3Afshar-Nadjafi B, Majlesi M. Resource constrained pro-ject scheduling problem with setup times after preemp-tive processes[J], Computers &- Chemical Engineering,2014,69: 16-25.
  • 4Browning T, Yassine A. Resource-constrained multi-project scheduling: Priority rule performance revisited[J]. International Journal of Production Economics,2010,126(2):212-228.
  • 5Lim A, Ma Hong, Rodrigues B,et al. New conceptsfor activity float in resource-constrained project manage-ment[J]. Computers Operations Research,2011,38(6): 917-930.
  • 6Cheng Minyuan,Tran D H, Wu Yuwei. Using a fuzzyclustering chaotic-based differential evolution with serialmethod to solve resource-constrained project schedulingproblems[J]. Automation in Construction, 2014,37 :88-97.
  • 7Azaron A,Katagiri H, Sakawa M. Time-cost trade-offvia optimal control theory in Markov PERT networks[J]. Annals of Operations Research, 2007,150(1) : 47-64.
  • 8Xu Jiuping, Zheng Huan,Zeng Ziqiang,et al. Discretetime-cost-environment trade-off problem for large-scaleconstruction systems with multiple modes under fuzzyuncertainty and its application to J inping-II Hydroelec-tric Project[J]. International Journal of Project Manage-ment, 2012,30(8): 950 - 966.
  • 9宁晓倩,王其藩.运用系统动力学模型进行项目时间/成本估算[J].科技导报,2004,22(9):54-57. 被引量:9
  • 10Tavana M, Abtahi A R, Khalili-Damghani K. A newmulti-objective multi-mode model for solving preemp-tive time - cost - quality trade-off project schedulingproblems [J], Expert Systems with Applications,2014,41(4): 1830-1846.

二级参考文献107

共引文献128

同被引文献294

引证文献33

二级引证文献148

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部