摘要
以巴彦高勒矿311101工作面为背景,采用现场测试、理论计算和数值模拟相结合的方法,在揭示大采高综采工作面侧向支承压力分布规律基础上,研究不同宽度区段煤柱应力场及塑性区分布特征,最后确定合理区段煤柱宽度。研究表明:煤柱宽度15~20 m时,煤柱中央仍有一定弹性核,煤柱稳定。考虑煤炭资源回收和巷道围岩稳定等因素,确定区段煤柱宽度为15 m。
In this paper, taking 311101 working face of Bayangaole Mine as engineering background, using field testing, theoretical calculations and numerical simulation methods, on the basis of revealing abutment pressure distribution laws of large fully mechanized mining face, we study different widths pillar stress field and distribution of plastic zone. Finally, we determine a reasonable section of coal pillar width. Studies show that: when pillar width is 15 to 20 m, there is still a certain elastic nuclear in central coal pillar, coal pillar remains stable. Considering the coal resource recovery and roadway stability and other factors, we determine that the Ordos region fully mechanized mining face of coal pillar reasonable width is 15 m.
出处
《煤矿安全》
CAS
北大核心
2016年第2期66-68,72,共4页
Safety in Coal Mines
基金
国家自然科学基金资助项目(51344009)
矿山灾害预防控制省部共建国家重点实验室培育基地开放课题基金资助项目(MDPC2013KF12)
山东省"泰山学者"建设工程专项经费资助项目
山东省优秀中青年科学家科研奖励基金资助项目(BS2012NJ007)
山东科技大学教改资助项目
关键词
综采工作面
侧向支承压力
区段煤柱
数值模拟
塑性区
full-mechanized coal caving face
side abutment pressure
segment pillar
numerical simulation
plastic zone
作者简介
卢国豪(1988-),男,河南平顶山人,中国矿业大学在读硕士研究生,主要从事变形监测及沉陷控制方面的研究工作。