本文以高寒地区混凝土井塔快速施工中的关键技术作为研究对象,对混凝土井塔冬期施工方案进行了阐述,对快速解冻人工冻融土技术以及快速施工的套成技术展开了深入地研究。
This paper takes the key technology of rapid con-struction of concrete tower in alpine area as the research object, expounding the winter construction scheme of concrete shaft tower, and deeply studied the rapid thawing of the artificial frost thawed soil technology and rapid construction technol-ogy.