已服役20年预应力结构现存预应力的试验研究 被引量:7

Experimental study on the extant pre-stressed force in 20-year old prestressed structure
在线阅读 下载PDF
导出
摘要 为了探讨在役预应力混凝土梁中现存预应力值,利用应力释放法对已经服役20年的预应力空心板梁进行切槽法试验。研究了不同的切割位置,切割缝间距对测点应力释放速度的影响;分析了切槽法释放混凝土工作应力随切槽深度、切割缝间距的变化规律,得到了梁体混凝土工作应力得以全部释放的切槽深度;利用数值分析软件建立切割深度与测点残余应力之间的拟合函数,从而推断出梁底表面的初始应力;根据推导的混凝土现存预应力的计算公式,将推导得到的初始应力代入计算公式,获得梁体现存预应力,通过这种方法实现对梁现存预应力的准确预估,以期对混凝土结构有效预应力的评估和桥梁结构评定方法提供一定的参考。 In order to study the extant pre-stressed force in the pre-stressed concrete beam,the stress-releasing method on the pre-stressed hollow slab beam which had served for 20 years was used in the grooving test. The effects of different cutting positions and cutting gap spacing on the testing stress release rate are researched. The variation law of the release concrete working stress with the changing of the notch depth and gap spacing in the grooving test was analyzed,achieving the depth of notch when the working stress of beam concrete was release completely. The fitting function between the cutting depth and the measured residual stress was established using numerical analysis software,so as to deduce the surface initial stress of the beam bottom. According to the derived formula of existing prestress of concrete,the initial stress generated from the derivation was substituted into the calculation formula,so as to get extant pre-stress of the beam. By this method the extant pre-stressed force of beam was accurately estimated. This paper provided reference to a certain extent for effective pre-stress evaluation and assessment of bridge structure.
作者 黄颖 房贞政
出处 《哈尔滨工程大学学报》 EI CAS CSCD 北大核心 2014年第10期1201-1205,共5页 Journal of Harbin Engineering University
基金 国家自然科学青年基金资助项目(51108092) 福建省交通科技资助项目(201336)
关键词 在役预应力简支梁 应力释放 切槽法 现存预应力 拟合函数 in-service pre-stressed simply supported beam stress-releasing grooving method extant pre-stressed force fitting function
作者简介 黄颖(1982-),女,讲师,博士研究生;通信作者:黄颖,Email:huangying6820@163.com. 房贞政(1949-),男,教授,博士生导师.
  • 相关文献

参考文献16

  • 1吕志涛,潘钻峰.大跨径预应力混凝土箱梁桥设计中的几个问题[J].土木工程学报,2010,43(1):70-76. 被引量:67
  • 2JTGD62-2004公路钢筋混凝土及预应力混凝土桥涵设计规范[S],北京:人民交通出版社,2004.
  • 3STEINBERG E P. Probabilisstic assessment of prestress loss in pretensioned prestressed concrete [ J ]. PCI Journal, 1995, 40(6): 76-85.
  • 4GHOTHAN P A I. Magnetie-based NDE of steel in pres-tressed and post-tensioned concrete bridges[J]. Proceedings of SPIE:The International Society for Optical Engineering, 1998, 3400(1): 343-347.
  • 5MA J I, ARUP K, NEGRET I. Smart prestressing with shape- memory alloy[J]. Journal of Engineering Mechanics, 1998, 124(10) : 1121-1128.
  • 6HELENE P,PEREIRA M F,CASTRO P. Performance of a 40-year-old concrete bridge with embedded, prestressed gal- vanized strands [ J]. Materials Performance, 2004, 43 (10) : 42-45.
  • 7FOWLER T J, YEPEZ L O, BAMES C A. Acoustic emission monitoring of reinforced and prestressed concrete structures [ J]. Proceedings of SPIE : The International Society for Opti- cal Engineering, 1998, 34(1) : 281-298.
  • 8吴东云,杨树标,安新正.钢结构工作应力测定试验研究[J].煤矿设计,2000(6):27-28. 被引量:9
  • 9MATHER J. Determination of initial stress by measuring the deformation around drilled hole [ J ] .Trans ASME, 1934, 56: 103-114.
  • 10SASAKI K, KISHIDA M, LTOH T. The accuracy of resid- ual stress measurement by the hole-drilling method [ J ] .Ex- perimental Mechanics, 1997, 37 (3) : 250-257.

二级参考文献28

共引文献302

同被引文献70

引证文献7

二级引证文献20

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部