摘要
本文通过工程实例介绍人工挖孔桩施工中遇流沙、流泥现象时的施工技术措施 。
The construction technical steps when the flowing sand mud are encountered during the construction period are introduced.Some engineering cases are also presented in this paper.
出处
《福建建筑》
2000年第B11期32-35,共4页
Fujian Architecture & Construction
关键词
人工挖孔桩
流砂
流泥
工程施工
hand-dug pile flowing sand Flowing mud Belled Step