摘要
本文以珠三角城际轨道交通佛山-肇庆段控制性工程羚山长隧道施工为例,结合该隧道工程的地质、水文、气候条件;为确保该工程的安全与质量,采取了施工超前地质预报技术,文章对该项技术的关键部分做了精辟的探讨,该技术不仅适用于羚山长隧道的施工,而且对其它类似工程的施工都有着非常重要的借鉴意义。
Based on the Pearl kiver Delta inter-city rail transit Foshan Zhaoqing control engineering Ling mountain long tunnel construction as an example, combined with geologylhydrology, climate conditions of the tunnel engineering;in order to ensure the safety and quality of the project, adopt the advanced geological forecast technology in construction,made a brilliant of the key parts of the technology the construction,the technology is not only applicable to the current mountain long tunnel, and the construction of other similar projects have a very important significance.
出处
《中国建材科技》
2013年第2期96-98,共3页
China Building Materials Science & Technology
关键词
城际轨道交通
超前地质预报
隧道
关键技术
Lintercity rail transit
advance geological forecast
tunnel
key technologykey