基于随机活动工期的资源约束项目鲁棒性调度优化 被引量:20

Robust scheduling optimization for resource-constrained project based on random duration of activities
原文传递
导出
摘要 项目进度计划的鲁棒性对于不确定条件下项目的顺利实施具有重要影响.作者研究具有随机活动工期的资源约束项目鲁棒性调度问题,目标是在可更新资源和项目工期约束下安排活动的开始时间,以实现项目进度计划鲁棒性的最大化.首先对所研究问题进行界定并用一个示例对其进行说明.随后构建问题的优化模型,设计禁忌搜索、多重迭代和随机生成三种启发式算法.最后在随机生成的标准算例集合上对算法进行测试,分析项目活动数、项目工期和资源强度等参数对算法绩效的影响,并用一个算例对研究进行说明,得到如下结论:禁忌搜索的满意解质量明显高于其他两种算法;当资源强度或项目工期增大时,平均目标函数值上升,禁忌搜索的求解优势增强.研究结果可为不确定条件下项目进度计划的制定提供决策支持. The robustness of project schedule plays an important role for the smooth execution of project under uncertain conditions. The authors studied the resource-constrained project robust scheduling prob- lem with random duration of activities. The objective was to arrange the start time of activities so as to maximize the robustness of project schedule under the constraints of renewable resources and project duration. The studied problem was identified and illustrated by using an example at first. Then the opti- mization model was constructed and three heuristic algorithms, including tabu search, multiple iteration, and random generation, were developed. Ultimately, the algorithms were tested on a standard instance set generated randomly. The influences of activity number, project duration, and resource strength on the algorithms' performance were analyzed. An instance was utilized to illustrate the research in the paper and the following conclusions were drawn: The solution quality of the tabu search is remarkably higher than that of the other two algorithms; as the resource strength or the project duration increase, the average value of objective function climbs and the quality advantage of the desirable solution of the tabu search augments. The research in this paper can provide decision supports for the preparation of project schedule under uncertain conditions.
出处 《系统工程理论与实践》 EI CSSCI CSCD 北大核心 2013年第3期650-659,共10页 Systems Engineering-Theory & Practice
基金 国家自然科学基金(70971105) 陕西省自然科学基金(2009JM9001) 中央高校基本科研业务费专项资金
关键词 资源约束项目调度 优化模型 启发式算法 随机活动工期 鲁棒性 resource-constrained project scheduling optimization model heuristic algorithm randomduration of activities robustness
作者简介 何正文(1967~),副教授,博士,研究方向:项目管理及优化,E—maihzhengwenhe@mail.xjtu.edu.cn
  • 相关文献

参考文献19

  • 1Kolisch R, Padman R. An integrated survey of deterministic project scheduling[J]. Omega, 2001, 29(3): 249-272.
  • 2刘士新,王梦光,唐加福.资源受限工程调度问题的优化方法综述[J].控制与决策,2001,16(B11):647-651. 被引量:24
  • 3汪嘉旻,孙永广,吴宗鑫.时间和费用具有不确定性的优化进度计划[J].系统工程理论与实践,2002,22(1):93-98. 被引量:17
  • 4寿涌毅,王伟.基于鲁棒优化模型的项目调度策略遗传算法[J].管理工程学报,2009,23(4):148-152. 被引量:34
  • 5Herroelen W, Leus R. The construction of stable project baseline schedules[J]. European Journal of Operational Research, 2004, 156: 550-565.
  • 6Van de Vonder S, Demeulemeester E, Herroelen W, et al. The use of buffers in project management: The trade-off between stability and makespan[J]. International Journal of Production Economics, 2005, 97: 227-240.
  • 7Van de Vonder S, Demeulemeester E, Herroelen W, et al. The trade-off between stability and makespan in resource-constrained project scheduling[J]. International Journal of Production Research, 2006, 44(2): 215-236.
  • 8A1-Fawzan M A, Haouari M. A bi-objective model for robust resource-constrained project scheduling[J]. Inter- national Journal of Production Economics, 2005, 96: 175-187.
  • 9Lambrechts O, Demeulemeester E, Herroelen W. A tabu search procedure for developing robust predictive project schedules[J]. InternationM Journal of Production Economics, 2008, 111: 493-508.
  • 10Van de Vonder S, Demeulemeester E, Herroelen W. Proactive heuristic procedures for robust project scheduling: An experimental analysis[J]. European Journal of Operational Research, 2008, 189: 723-733.

二级参考文献31

  • 1王宏,林丹,李敏强.求解模糊资源受限项目调度问题的遗传算法[J].系统工程学报,2006,21(3):323-327. 被引量:13
  • 2冯允成.活动网络分析[M].北京:北京航空航天大学出版社,1992..
  • 3Kolisch R, Padman R. An integrated survey of deterministic project scheduling[J]. Omega, 2001, 3(29): 249- 272.
  • 4Kolisch R, Hartmann S. Experimental investigation of heuristics for resource-constrained project scheduling: An update. European Journal of Operational Research[J], 2006, 174: 23- 37.
  • 5Demeulemeester E, Herroelen W. Introduction to the special issue: project scheduhng under uncertainty [ J ]. Journal of Scheduling, 2007, 10(3): 151- 152.
  • 6Herroelen W, Leus R. Robust and reactive project scheduling: a review and classification of procedures [ J ]. International Journal of Production Research, 2004, 42(8) : 1599 - 1620.
  • 7Herroelen W, Leus R. Project scheduling under uncertainty: Survey and research potentials [ J ]. European Journal of Operational Research, 2005, 165: 289-306.
  • 8Vonder S V D, Demeulemeester E, Herroelen W. A classification of predictive-reactive project scheduling procedures [ J ]. Journal of Scheduling, 2007, 10(3) : 195 - 207.
  • 9Mohring R H, Radermacher F J, Weiss G. Stochastic scheduling problems Ⅰ-General strategies [ J ]. Mathematical Methods of Operations Research, 1984, 28(7) : 193-260.
  • 10Mohring R H, Radennacher F J, Weiss G. Stochastic scheduling problems Ⅱ -Set strategies [ J ]. Mathematical Methods of Operations Research, 1985, 29(3) : 65 - 104.

共引文献70

同被引文献124

引证文献20

二级引证文献124

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部