古城水电站深基坑开挖方案探讨 被引量:1

Discussion on Excavation Schemes for Deep Flundation Pit of Gucheng Hydropower Station
在线阅读 下载PDF
导出
摘要 结合古城水电站厂房基础开挖,对深基坑支护技术进行了探讨,介绍了支护方案及其投资,进行了方案比选,并重点对地下连续墙方案进行了边坡稳定计算,结果满足规范的要求,表明地下连续墙方案在投资及施工方面具有一定的可行性;深基坑方案可有效地减少开挖量,但风险较大。 The application of supporting techniques for deep foundation pit in powerhouse excavation of Gucheng Hydro- power Station is discussed. Supporting schemes and their investment are introduced and compared. The side slope stability of underground continuous walls is calculated and its results meet the requirements of specification, which indicate that underground continuous walls are feasible in terms of investment and construction and that the deep foundation pit scheme has the features of decreased excavation quantity but with higher risk.
出处 《水电与新能源》 2012年第5期46-49,共4页 Hydropower and New Energy
关键词 深基坑 钻孔灌注桩 地下连续墙 边坡稳定 deep foundation pit drilling pile underground continuous wall side slope stability
作者简介 吴坤明,女,工程师,从事水道及厂房的研究与设计工作。
  • 相关文献

参考文献5

二级参考文献21

  • 1王雁然.[D].武汉:武汉工业大学,1999.
  • 2TerZaghi K, Peck R B. Soil Mechanics in Engineering Practice[ J ].2nd ed John Wiley&Sons Inc New York, 1967,729.
  • 3Tschebotorrioff G P. Foundations. Retaining and Earth Structures[ J]. 2nd ed. McGraw Hill Book Company New York, 1973,642.
  • 4Dou Yuanming. A Model Test of Excavation Deep Foundation PIT and Finite Element Analysis [A]. The Fifth International Conference on Tall Buildings [C]. HongKong, 1998, 872-877.
  • 5Liu Xiyuan, Dou Yuanming, Yan Shuwang. Study on Technology and Safty Measures for Supporting Structures around Deep Foundation Pit [A].Progress in Safty Science and Technolpogy [C], Taian, 2002.
  • 6刘小丽.[D].天津:河北工业大学,2000.
  • 7刘熙嫒.[D].天津:天津大学,2003.
  • 8河北工业大学土木工程学院.河北省深基坑支护技术的现状与对策科研报告[R].,2001..
  • 9陈继芳.深基坑开挖变形引起临近建筑物、地表沉陷分析[A]..第七届全国地基处理学术讨论会论文集[C].兰州,2002..
  • 10严华.[D].天津:河北工业大学,2003.

共引文献443

同被引文献10

引证文献1

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部