盾构在水平冻结加固区小半径曲线始发技术 被引量:6

Launching Technologies for Shield Machine on Curve with Small Radius in Soil Consolidated by Horizontal Freezing Method
在线阅读 下载PDF
导出
摘要 无锡地铁1号线江海路站—火车站区间盾构始发处在半径360 m曲线上,且始发端头上部有河道、桥梁及多条大直径市政管线,盾构始发处在多个风险高度集中地段,风险和施工难度极大。为保证盾构顺利始发,并确保上部河流、桥梁和管线的安全,采用初始段的割线始发技术,避免小半径曲线纠偏造成的超挖;采用水平冻结加固技术并通过采取蒸汽解冻配合割线始发的综合技术通过冻结加固区,保证了盾构的安全顺利始发。 The shield launching section of Jianghai Road StationRailway Station section on No. 1 line of Wuxi Metro is on a curve with 360 m radius. There are rivers, bridges and largediameter municipal pipelines above the shield launch ing head. There are many risks and great construction difficulties. Secant launching technology at primary section is a dopted, so as to guarantee the successful launching and the safety of the river, bridges and pipelines, and to avoid over break. Horizontal freezing technology and consolidated section passing through technology by means of steam thawing combined with secant launching technology are used.
出处 《隧道建设》 2012年第4期531-536,共6页 Tunnel Construction
关键词 盾构 水平冻结加固 割线始发 小半径曲线 shield machine soil consolidation horizontal freezing method secant launching curve with small radius
作者简介 李义华(1969-),男,河南平舆人,2009年毕业于河北工业大学电子信息专业,本科,工程师,现从事施工管理工作。
  • 相关文献

参考文献10

二级参考文献49

共引文献154

同被引文献54

引证文献6

二级引证文献35

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部