巴基斯坦集装箱深水港防波堤工程Core-Loc块体预制的质量控制 被引量:2

Quality Control for Precasting of Core-Loc Units for Breakwater Project for a Deep Water Container Terminal in Pakistan
在线阅读 下载PDF
导出
摘要 结合巴基斯坦集装箱深水港防波堤工程和Core-Loc块体的预制过程的实际情况,通过对巴基斯坦当地的部分工程施工条件的现场调查,从人、机、料、法、环五个方面分析影响块体预制质量的5个主要原因,并制定了不同的对策及实施过程,为以后类似工程的施工积累经验。 In the light of the actual situations in the construction of the breakwater and the prefabrication of Core-Loc Units for a deep water container terminal in Pakistan and based on the field surveys of some local projects in Pakistan, the five main factors, such as manpower, machinery, material, methodology and environment, which affect the quality of the precast Core-Loc Units, were analyzed. On the basis of the analyses, different counter-measures and implementing procedures to fulfill them were formulated, gaining experience for similar future works.
出处 《中国港湾建设》 2012年第1期39-41,共3页 China Harbour Engineering
关键词 巴基斯坦 Core-Loc块体 预制 质量控制 Pakistan core-loc unit prefabrication quality control
作者简介 作者简介:薛瑞龙(1984-),男,重庆市人,助理工程师,港口、海岸及近海工程专业。
  • 相关文献

参考文献3

二级参考文献6

  • 1白银战,庄正勇.港口工程中扭王字块应用标准的比较[J].水运工程,2005(11):36-39. 被引量:7
  • 2JTJ270-98.水运工程混凝土试验规程[S].[S].,..
  • 3JTJ221—98.港口工程质量检验评定标准[S].[S].,..
  • 4JTJ268—96,水运工程混凝土施工规范[S].
  • 5JTJ/T273—97,港口工程粉煤灰混凝土技术规程[S].
  • 6第一航务工程局.港口工程施工手册(上册)[M].北京:人民交通出版社,1994.

共引文献5

同被引文献2

引证文献2

二级引证文献3

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部