摘要
天然河流上游修建大型水利枢纽后,必将引起水库下游河道的再造床。黄河小浪底水库自1999年10月下旬下闸蓄水以来,已运行十年有余。本文通过实测资料的分析,从河道的冲刷和河道的平面形态变化两方面来阐明小浪底水库拦沙运用十年来水库淤积及下游河道的再造床过程及其特点,为小浪底水库进一步水沙调控提供借鉴,也丰富了多泥沙河流兴建大型水库以后下游河道河床演变学科的内涵。
The Xiaolangdi Hydro-Project is a large project downstream of the Sanmenxia Project in the Yel- low River playing the role of flood control and sedimentation mitigation. The reservoir has been operated for 10 years. Based on the field measured data, the reservoir sedimentation and the channel re-establishment of the Lower Yellow River including the morphology of the reservoir deposition, the density current and its sediment transport, the characteristics and efficiency of channel erosion, the coarsening of bed sediment and effects of channel armoring, the relationship between reservoir deposition and channel erosion, as well as the compensation index of reservoir deposition, are analyzed and expounded in this paper. These results are helpful to understand the new behavior of fluvial processes of the river carrying large amount of sediment load such as the Yellow River in the initial period of reservior operation.
出处
《水利学报》
EI
CSCD
北大核心
2012年第2期127-135,共9页
Journal of Hydraulic Engineering
基金
水利部公益性行业专项(200901014)
"十二五"国家科技支撑计划项目(2012BAB02B01)
国家973计划项目(2011CB409901)
关键词
水库淤积
河道冲刷
河道粗化
冲刷效率
水库淤积补偿指标
reservoir sedimentation
river channel erosion
armoring of bed sediment
efficiency of chan-nel erosion
compensation index of reservoir deposition
作者简介
陈建国(1962-),男,内蒙古呼和浩特人,教授级高级工程师,主要从事河流泥沙研究。E-mail:chenjg@iwhr.com