刘家峡水电站溢洪道增设检修闸门设计研究 被引量:7

Research on the addition of emergency gate for spillway of Lijiaxia hydropower station
在线阅读 下载PDF
导出
摘要 刘家峡水库联合调度以后,溢洪道堰顶露出的机会很少,溢洪道工作闸门及门槽失去了正常检修的条件。为确保溢洪道工作闸门正常运行,必须增设检修闸门以便对溢洪道工作闸门系统进行全面维护检修。就增设检修闸门的技术方案进行了认真研究,并对浮体检修门的封堵和止水进行了详细论证。 After the joint regulation of Liujiaxia reservoir,the top of spillway scarcely exposed,and there is no way to repair the service gate and slot regularly.In order to ensure the normal operation of the spillway service gate,it is necessary to add emergency gate so as to maintain and repair the service gate system of the spillway completely.The paper carefully studies the technical option concerning the addition of emergency gate,and justifies the blocking and water sealing of the floating emergency gate in detail.
出处 《西北水电》 2011年第3期76-79,共4页 Northwest Hydropower
关键词 溢洪道 浮体闸门 检修闸门 刘家峡水电站 spillway floating gate emergency gate Liujiaxia hydropower station
作者简介 方勇(1970-),男,甘肃省临夏市人,工程师,从事水利水电工程金属结构设计工作.
  • 引文网络
  • 相关文献

参考文献4

二级参考文献1

  • 1DL/T5039-95.水利水电工程钢闸门设计规范[S].[S].,..

共引文献3

同被引文献31

引证文献7

二级引证文献6

;
使用帮助 返回顶部