隧道爆破开挖条件下地表建筑振动速度响应研究 被引量:19

Research on vibration velocity responses of surface building under the condition of blasting excavation in tunnel
在线阅读 下载PDF
导出
摘要 为了研究隧道爆破开挖条件下地表建筑的振动速度响应规律,以福州高速公路魁岐1号隧道工程为例,对隧道上部地表建筑进行振动速度监测,同时结合隧道现场的实际施工情况,利用ANSYS/LS-DYNA动力有限元分析软件对隧道爆破开挖引起的地表建筑的振动速度响应进行了数值模拟。通过分析现场实测和数值模拟结果得出以下结论:对比不同爆源条件下,地表建筑测点的峰值振动速度随爆源距的增大而减小,而在相同爆源条件下,地表建筑测点的峰值振动速度随爆源距的增大呈现先减小而后迅速增大的现象;地表建筑测点的峰值振动速度随测点高度的增大有明显的放大效应,且测点高度越大,放大效应越明显;隧道开挖成型后的空洞对于地表建筑测点的峰值振动速度具有明显的空洞放大效应,且空洞距离建筑越近,放大效应越明显;考虑建筑测点峰值振动速度的空洞放大效应时,隧道开挖宜采用先开挖深埋硐室后开挖浅埋硐室的施工顺序。 In order to research the vibration velocity responses of surface building under the condition of blasting excavation in tunnel, the vibration velocity of surface building was monitored by taking Kui-qi 1# highway tunnel in Fuzhou city as an example. Meanwhile, with the actual construction of tunnel, the vibration velocity responses of the surface building under the condition of blasting excavation in tunnel were studied by use of the ANSYS/LS-DYNA dynamical finite-element program. The analysis of field measurement and numerical simulation results shows that: (a) Comparing the different explosive sources, the peak vibration velocities of measuring points in the surface building decrease with the increase of distance to explosive source. The peak vibration velocities of measuring points in the surface building decrease firstly and then highly increase with the increase of distance to explosive source for the same explosive sources; (b) The peak vibration velocities of measuring points in the surface building increase with the increase of the height of measuring points, the higher the measuring points, the more obvious the amplification effect; (c) The peak vibration velocities of measuring points in the surface building have obvious empty amplification, the smaller the distance between building and empty, the more obvious the amplification effect; (d) Considering the peak vibration velocity empty amplification effect of the surface building measuring points, the deeply buried cavern should be excavated before the shallow cavern.
出处 《地震工程与工程振动》 CSCD 北大核心 2010年第6期112-119,共8页 Earthquake Engineering and Engineering Dynamics
基金 国家自然科学基金项目(40902078) 贵州省科委重大科技项目(黔科合重大专项字[2008]6013)
关键词 隧道 爆破震动 地表建筑 峰值震速 放大效应 tunnel blasting vibration surface building peak vibration velocity amplification effect
作者简介 作者简介:张永兴(1961-),男,教授,博士,主要从事岩土工程方面的教学与研究工作.E—mail:cqyxzhang@163.com
  • 相关文献

参考文献10

二级参考文献36

  • 1姚勇,何川,晏启祥,李玉文.董家山隧道小净距段爆破控制的数值模拟[J].岩土力学,2004,25(z2):501-506. 被引量:36
  • 2张继春,曹孝君,郑爽英,郭学彬.浅埋隧道掘进爆破的地表震动效应试验研究[J].岩石力学与工程学报,2005,24(22):4158-4163. 被引量:130
  • 3李宏男,王炳乾,林皋.爆破地震效应若干问题的探讨[J].爆炸与冲击,1996,16(1):61-67. 被引量:37
  • 4攴国华.岩体的节理裂隙及断层对爆破地震波传播影响的动力分析[M].上海:同济大学,1994..
  • 5核工业西南地勘局.朝东岩隧道工程地质勘察报告[M].成都,1999..
  • 6中华人民共和国国家标准编写组.爆破安全规程(GB6722-86)[S].北京:冶金工业出版社,1986..
  • 7李斯海 王昆明.仙岳山隧道施工爆破振动测试及理论分析[A].林崇一编.第二届海峡两岸隧道与地下工程学术与技术研讨会论文集[C].台北:[s.n.],2001.536~544.
  • 8刘清泉.爆破工程师手册[M].北京:煤炭工业出版社,1992..
  • 9高晓初 吴子骏.运营隧道小间距平行隧道开挖爆破安全控制[A]..工程爆破文集第六辑[C].深圳:海天出版社,1997..
  • 10林学义 王兰民.隧洞的爆破地震动效应问题[A]..工程爆破文集第六辑[C].深圳:海天出版社,1997..

共引文献260

同被引文献178

引证文献19

二级引证文献116