大断面长溜井高位堵塞疏通处理实践研究 被引量:16

Practical Research on Dredging the High-level Blockage for a Long Large-section Chute
在线阅读 下载PDF
导出
摘要 介绍了新白马公司1#溜井在起用较短时间后就出现高位堵塞情况,通过对发生高位堵塞的类型的判断,对造成高位堵塞的原因进行了详细研究,同时制订了溜井高位堵塞的多种疏通处理方案,并加以实施最终将堵塞处贯通,总结分析露天矿山溜井在设计施工建设阶段和生产使用过程中的注意事项,以及如何避免发生溜井高位堵塞和溜井高位堵塞时的疏通处理方法。 This paper introduces the high-level blockage emergence in a short time in Xinbaima 1^# chute. By judging the type of high-level blockage, the causes for the blockage are elaborated and some dredge disposals are given. Then these disposals are implemented to eventually dredge the blockage. And some attention that should be paid in design and construction of open-pit mine chute and in production are analyzed,and how to prevent the high-level blockage and to dredge the blockage for mine chute are summarized.
出处 《金属矿山》 CAS 北大核心 2009年第10期39-41,44,共4页 Metal Mine
关键词 溜井 高位堵塞 气球爆破 疏通 Chute,High-level blockage,Balloon blasting,Dredge
作者简介 高文远(1965-),男,攀钢集团矿业有限责任公司,总经理助理;攀钢新白马矿业有限责任公司,经理,高级工程师,617200四川省攀枝花市米易县弯丘乡。
  • 相关文献

参考文献5

  • 1李宝祥.金属矿山露天开采[M].北京:冶金工业出版社.1986.
  • 2高文远.兰尖铁矿科技论文集[M].成都:四川科学技术出版社,2004.
  • 3中冶长天国际工程有限责任公司.白马铁矿初设说明技术资料(一期)[R].攀枝花:攀钢新白马有限责任公司,2005.
  • 4中冶长天国际工程有限责任公司.攀枝花钢铁集团公司白马铁矿一期工程平硐溜井系统1^#溜井矿建施工图[R].攀枝花:攀钢新白马有限责任公司,2005.
  • 5攀钢冶建特种公司.白马矿1^#溜井直(斜)溜井段工程地质素描图[R].攀枝花:新白马公司,2005.