摘要
结合西气东输二线西段管道建设,介绍了竣工资料管理、移交和资料整理应注意的问题。文章指出,工程建设项目的竣工资料管理工作应设专人负责,应制订统一明确的标准要求,应与工程建设项目的进度同步,要做到竣工资料数据的真实、准确、完整。
This paper introduces the matters needing attention in management, transfer and compilation of project completion data in association with the construction of West Section of Second West to East Gas Pipeline Project. It points out that the appointed personnel should take the responsibility of project completion data management work, the accordant and definite standard should be established, the data management work should be synchronously done with the project construction schedule, and the reality, exactness and integrity of project completion data should be guaranteed.
出处
《石油工程建设》
2010年第S1期203-205,307,共4页
Petroleum Engineering Construction