摘要
通过对广州市新光快速路与广州市地铁3号线平面位置重合路基地段地质情况的分析,提出了采用浅层换填土、水泥搅拌桩、气泡轻质土等多种地基处理方式,从而解决了新光快速路在地铁隧道上地基处理问题,并取得了良好的效果。
Through the analysis of the geological condition of the subgrade section of the plane position registration of metro No. 3 line and Xin- Guang expressway in Guangzhou, the author puts forward the foundation treatment methods of the shallow replacing and filling earth, the cement mixing pile and the bubble light soil, to solve the problem of the foundation treatment of Xin-Guang expressway on the subway tunnel, and the good results have been obtained.
出处
《山西建筑》
2008年第23期114-115,共2页
Shanxi Architecture
关键词
地铁
隧道
水泥搅拌桩
气泡轻质土
质量控制
subway, tunnel, cement mixing pile, bubble light soil, quality control
作者简介
梁剑雄(1972-),男,工程师,中国华西工程设计建设有限公司广州分公司,广东广州510620