摘要 金安桥工程实施截流时只有1号导流洞单洞导流,截流流量为829m3/s,最大落差4.72m,最大流速达7.15m/s,截流段河床地形、地质条件复杂,在截流模型试验成果基础上对截流过程中可能出现的困难进行了分析,按确定方案实施了截流,顺利实现了大江截流。 During river closure of the Jinanqiao Project, only No. 1 diversion channel was used for water diversion. The closure discharge was 829m^3/s, the maximum water head was 4.72m, and the maximum speed was 7.15m/s. The landform of riverbed in the section of river closure and geological conditions was complicated. Thus possible difficulties with river closure were examined on the basis of experiment results of river closure model. River closure was successfully completed according to the proposed plan.
作者 徐银林
出处 《中国水利》 2007年第6期47-48,共2页 China Water Resources
关键词 金安桥水电站 截流设计 施工 inanqiao Hydropower Station river closure construction
作者简介 徐银林(1964-),男,中国水利水电第四工程局副局长,高级工程师。
  • 相关文献

参考文献3

  • 1水利水电工程施工组织设计手册[C].北京:中国水利水电出版社,1994.
  • 2中国水力发电工程[C].北京:中国电力出版社.2000.
  • 3金安桥截流设计及原型试验成果[R],2005.

共引文献1

同被引文献21

引证文献2

二级引证文献5

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部