知识化制造系统中生产瓶颈的分析方法 被引量:13

Method of shifting bottleneck analysis in knowledge-oirented manufacturing system
在线阅读 下载PDF
导出
摘要 在产品的制造过程中,如果某些生产环节能力过于薄弱,将会形成瓶颈效应,阻碍其他部分生产能力的充分利用。为此,建立了知识化制造系统的网状模型,该模型适用于柔性生产线的生产瓶颈分析。在此基础上,提出了完备生产网络的概念和寻找完备生产网络中生产瓶颈的方法。利用自学习方法将瓶颈和其对应的生产条件存入瓶颈知识库,以便确定在不同生产条件下哪些环节需要改进。最后通过算例分析,证实了该瓶颈分析方法的有效性。 During the production process, some production links with weak capacity will become a bottleneck to obstruct the full utilization of the other links. To deal with this problem, a net-like model of the knowledge-oriented manufacturing system was constructed which was applicable in bottleneck analysis in flexible product line. Based on the model, a concept of complete production net and a method to define bottlenecks in complete production nets were proposed. Furthermore a self-learning method was adopted to save knowledge of bottlenecks and corresponding production conditions in the knowledge base to determine which link needed to be improved under different production circumstances. Finally the example demonstrated the effectiveness of the bottleneck analysis method.
出处 《计算机集成制造系统》 EI CSCD 北大核心 2006年第2期271-279,共9页 Computer Integrated Manufacturing Systems
基金 国家自然科学基金资助项目(60443001 50475075) 江苏省高校"青蓝工程"第二期省级中青年学术带头人培养计划。~~
关键词 知识化制造 生产瓶颈 自学习 知识化制造单元 knowledgeable manufacturing production bottleneck self- learning knowledgeable manufacturing cell
作者简介 施文武(1976-),男,江苏盐城人,东南大学自动化研究所博士研究生,主要从事知识化制造、人工智能等的研究。E—mail:shiwenwu2005@163.com。
  • 相关文献

参考文献10

  • 1张晓东,严洪森.一类Job-shop车间生产计划和调度的集成优化[J].控制与决策,2003,18(5):581-584. 被引量:43
  • 2陈启申.约束理论[J].计算机集成制造系统-CIMS,1998,4(5):51-55. 被引量:25
  • 3MOSS H K,YU W B.Toward the estimation of bottleneck shiftiness in a manufacturing operation[J].Production and Inventory Management Journal,2000,40(2) :53-58.
  • 4ROSER C,NAKANO M,TANAKA M.Shifting bottleneck detection[A].Proceeedings of the 2002 Winter Simulation Conference[C].New York,NY,USA:IEEE,2002.1079 - 1086.
  • 5KUO C T,LIM J T,MEERKOV S M.Bottlenecks in serial production lines:a systems approach[A].Proceedings of the 35 th Conference on Decision and Control[C].Piscataway,NY,USA:IEEE,1996.2751-2756.
  • 6CHIANG S Y,KUO C T,MEERKOV S M.DT-bottleneeks in serial production lines:theory and application[J].IEEE Transaction Robotics and Automation,2000,5 (16):567 -580.
  • 7CHIANG S Y,KUO C T,MEERKOV S M.Bottlenecks inMarkovian production lines:a systems approach [J].IEEETransaction Robotics and Automation,1998,2 (14):352 - 359.
  • 8LI Jingshan,MEERKOV S M.Bottlenecks with respect to due -time performance in pull serial production lines[A].Proceedings of the 2000 IEEE International Conference on Robotics & Automation[C].Piscataway,NY,USA:Institute of Electrical and Electronics Engineers Inc.,2000.2635-2640.
  • 9HUANG Wenqi,YIN Aihua.An improved shifting bottleneck procedure for the job shop scheduling problem[J].Computers & Operations Research,2004,12(31):2093- 2110.
  • 10RAMUDHIN A,MARIER P.The generalized shifting bottle neck procedure [J].European Journal of Operational Research,1996,93(1):34-48.

二级参考文献9

  • 1Yan Hongsen. Hierarchical stochastic production planning with delay interaction [J]. J of Optimization Theory and Applications, 2000,104(3):659-689.
  • 2Lasserre J B. An integrated model for job-shop planning and scheduling[J]. Management Science, 1992, 38(8):1201-1211.
  • 3Anwar M F,Nagi R. Integrated lotsizing and scheduling for just-in-time production of complex assemblies with finite set-up[J].Int J of Production Research,1997,35(5):1447-1470.
  • 4Haase K, Kimms A. Lot sizing and scheduling with sequence-dependent setup costs and times and efficient rescheduling opportunities [J ]. Int J Production Economics, 2000, 66(2): 159-169.
  • 5Kimms A. A genetic algorithm for multi-level, multimachine lot sizing and scheduling [J]. Computers & Operations Research, 1999, 26(8): 829-848.
  • 6Knosala R, Wal T. A production scheduling problem using genetic algorithm[J]. J of Materials Processing Technology, 2001, 109(1-2): 90-95.
  • 7Cheng Runwei, Gen Mitsuo, Tsujimura Yasuhiro. A tutorial survey of job-shop scheduling problems using genetic algorithms--Part II: Hybrid genetic search strategies [J]. Computers & Industrial Engineering,1999. 36(2):343-364.
  • 8Li Y, Ip W H, Wang D W. Genetic algorithm approach to earliness and tardiness production scheduling and planning problem [J]. Int. J Production Economics,1998, 54(1): 65-76.
  • 9严洪森,张晓东.最优递阶随机生产计划与控制[J].自动化学报,2002,28(1):83-89. 被引量:4

共引文献66

同被引文献94

引证文献13

二级引证文献46

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部