巨野矿区彭庄矿主、副井冻结施工技术

Freezing alluvium technology of the chief and auxiliary shaft of pengzhuang colliery in juye coalfield
在线阅读 下载PDF
导出
摘要 彭庄矿井表土段采用冻结法施工,由于精心安排,认真分析,掘砌过程中现场实测,创造出良好的掘砌条件,冻结总工期比设计提前了63天。由于对巨野矿区认识不足区,采用245m处套内壁。本文具体论述了上部砂层和下部粘土层施工的具体对策,使主、副井安全、快速的通过了表土和风化基岩段, The shaft sinking of pengzhuang colliery was used freezing alluvium technology.The paper summarizes the experiential and technical assistance used in construction,which makes the total process advance sixty-three days.However,for the lack of proper data,the process was once forced to pause to build the inner shaft at the depth of two hundred and forty-five meters.This paper also specially illustrate and analyse the upper quartz and the under alluvium,and it assures the safe and speedy construction.
出处 《煤矿现代化》 2006年第z1期24-25,共2页 Coal Mine Modernization
关键词 冻结 优化 设计 快速 施工 refrigeration device speedy construction
作者简介 逯心杰,男,1999年毕业于中国矿业大学建工学院矿井建设专业.现任兖州矿业集团新陆冻结安装有限公司项目部技术副经理,一直从事地层冻结技术的应用,发表论文两篇.
  • 相关文献

相关作者

内容加载中请稍等...

相关机构

内容加载中请稍等...

相关主题

内容加载中请稍等...

浏览历史

内容加载中请稍等...
;
使用帮助 返回顶部