摘要
浍河灌区干渠城区绛山路段由明渠改造为PCCP管道,文中按照PCCP管道施工流程进行论述,重点探讨解决钢板桩临时支护过程当中所遇到的各种难题及采取的措施,进而保证工程质量安全.
The Jiangshan downtown section of the main canal section of the Huihe Irrigation District was transformed from an open channel to a PCCP pipeline.According to the construction process of the PCCP pipeline,this paper discusses the various difficulties encountered in the process of temporary support of steel plate piles and the measures taken to ensure the quality and safety of the project.
出处
《山西水利科技》
2019年第2期28-30,39,共4页
Shanxi Hydrotechnics
关键词
钢板桩
流程
偏移
倾斜
控制
steel sheet pile
process
migration
tilt
control
作者简介
刘志鹏(1984一),男,2016年毕业于太原理工大学水利水电工程专业,工程师。