摘要
该文通过超长地下连续墙钢筋笼吊装实例,对钢筋笼荷载、吊点间距、钢筋笼挠度及钢丝绳受力进行计算,并对钢筋笼吊装进行说明。对类似工程施工有借鉴意义。
In this paper,through the example of hoisting reinforcement cage of super long diaphragm wall,the load of reinforcement cage,distance between lifting points,deflection of reinforcement cage and stress of steel wire rope are calculated,and the hoisting of reinforcement cage is explained.It has reference significance for similar engineering construction.
作者
宋宏伟
张海东
李成武
许洪亮
Song Hongwei;Zhang Haidong;Li Chengwu;Xu Hongliang(China Gezhouba Group No.1 Engineering Co.,Ltd.;Zhongkan Metallurgical Geotechnical Investigation Design&Research Instiute Co.,Ltd.)
出处
《勘察科学技术》
2020年第5期39-42,共4页
Site Investigation Science and Technology
关键词
地下连续墙钢筋笼
吊点
间距
挠度
钢丝绳
reinforcing cage of the underground diaphragm wall
lifting point
spacing
deflection
wire rope
作者简介
宋宏伟(1983-),男,高级工程师,土木工程专业。