以乌兹别克斯坦的Kizil Tepa泵站为背景,介绍其基本概况后,引入地质条件及方案选择,以围堰施工流程为指导,介绍施工期流水控制、拦水围堰填土及编织袋填充土方、迎水面铺设塑料薄膜及编制袋土堆砌、背水面抽取剩余水、主体工程改造、修复、验收、拦水围堰抽除的方案及注意事项等,采用以上技术措施,施工效果较好,且节约施工成本。
Based on uzbekistan Kizil Tepa pump station as the background,introduced the basic situation,after introducing the geological condition and the scheme selection,guided by the cofferdam construction process,introduces the construction flow control,Lan Shui cofferdam filling and woven bag filling earthwork,to meet the water laying plastic film and soil pile weave bags,to take back the water,the remaining water,main body engineering alteration,repair,acceptance,Lan Shui pumping schemes of the cofferdam and the matters needing attention,etc.,using the above technical measures,the construction effect is good,and save construction cost.
作者
王松波
王超超
韩先萍
毕国元
巩晓雷
WANG Songbo;WANG Chaochao;HAN Xianping;BI Guoyuan;GONG Xiaolei(HBCG International Engineering Construction Co.,Ltd.,Shijiangzhuang,Hebei 050051,China)
出处
《施工技术》
CAS
2019年第S01期1404-1406,共3页
Construction Technology
关键词
水坝
加固与改造
围堰
应用
施工技术
dam
reinforcement and reconstruction
cofferdam
application
construction
作者简介
王松波,高级工程师,E-mail:1817623478@qq.com