摘要
在隧道开挖过程中,超前地质预报已成为准确预报隧道前方围岩地质情况的有效方法,其中TSP法是较为成熟、直接的预报方法。结合凤凰岭隧道实体工程,采用TSP地震预报法,对隧道施工过程的断层破碎带、塌方、软岩和水进行了较为精准的超前预报,为确定合理的隧道开挖支护方案提供技术支持。
In the process of tunnel excavation,the advanced geological forecast has become an effective method to accurately forecast the geological situation of the surrounding rocks in front of the tunnel,among which the TSP method is a more mature and direct method.According to the solid project of Fenghuangling Tunnel,the TSP earthquake forecast method is adopted to accurately forecast the fault fracture zone,collapse,soft rock,and water in the tunnel construction,which provides technical support for determining reasonable tunnel excavation and support schemes.
作者
吕宏宇
LÜ Hong-yu(Shanxi Jinyang Expressway Reconstruction and Expansion Project Management Co.,Ltd.,Jincheng Shanxi 046000,China)
出处
《山西交通科技》
2023年第2期90-92,102,共4页
Shanxi Science & Technology of Transportation
关键词
隧道施工
工程地质
超前地质预报
TSP法
tunnel construction
engineering geology
advanced geological forecast
TSP method
作者简介
吕宏宇(1985—),男,山西五台人,高级工程师,2010年毕业于长安大学道路桥梁与渡河工程专业。