Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving heig...Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving height was 11.2 m. The gateroad pillar between panels was 38 m. During retreat mining,serious bumps occurred in the gateroads on both sides of the pillar affecting safety production. Therefore,pillarless mining was experimented. Using numerical modeling and comparative study of cases of similar mining condition,it was decided to employ a 6 m wide pillar,rather than the previous 38 m wide pillar.Support system for the gateroads was designed and implemented. During gateroad development,pillar failure conditions and entry deformation were monitored. Hydraulic fracturing method was employed to cut off the K3 sandstone along the entry rib so as to reduce the abutment pressure induced during retreat mining. Support reinforcement method combining grouting and advanced reinforcement methods was proposed to insure stable gateroad ahead of mining. Methane drainage and nitrogen injection were implemented to eliminate hazards associated with mine fire and spontaneous combustion. Since the development of gateroad has just completed,and retreat mining has not begun,the effectiveness of the proposed methods is unknown at this point. However,monitoring will continue until after mining.The results will be published in a separate paper.展开更多
A mechanical model to control the top-coal deformation is established in accordance with the structural characters of the gob-side entry surrounding rock for the fully-mechanic top-coal caving; the analytical solution...A mechanical model to control the top-coal deformation is established in accordance with the structural characters of the gob-side entry surrounding rock for the fully-mechanic top-coal caving; the analytical solution of top coal roof-sag curve is deduced with Winkler elastic foundation beam model. By means of a calculating and analytic program, the top coal roof-sag values are calculated under the conditions of different supporting intensities, widths of narrow pillars and stiffness of top coal; meanwhile, the relationship between the roof-sag values and supporting intensity, width of narrow pillars and stiffness of top coal is analyzed as well. With the actual situation of the gob-side entry taken into consideration, the parameters of top-coal control are determined and a supporting plan is proposed for the top-coal control,which is proved to be reliable and effective by on-site verification. Some theoretical guidance and advice are put forward for the top-coal deformation control in gob-side entry for fully mechanized top-coal caving face.展开更多
基金funded by the United Foundation key project fund,Chinese Natural Science Committee (No.U1261207)Datong Coal Group,Tashan Coal Mine,and supported by the Natural Science Foundation of Ningbo of China (No.U1261207)
文摘Coal seams in Tashan Mine of Datong Coal Group in China average 15 m thick and have been mined by the top coal caving longwall mining method of large mining height. Mining height was 3.8 m and the top coal caving height was 11.2 m. The gateroad pillar between panels was 38 m. During retreat mining,serious bumps occurred in the gateroads on both sides of the pillar affecting safety production. Therefore,pillarless mining was experimented. Using numerical modeling and comparative study of cases of similar mining condition,it was decided to employ a 6 m wide pillar,rather than the previous 38 m wide pillar.Support system for the gateroads was designed and implemented. During gateroad development,pillar failure conditions and entry deformation were monitored. Hydraulic fracturing method was employed to cut off the K3 sandstone along the entry rib so as to reduce the abutment pressure induced during retreat mining. Support reinforcement method combining grouting and advanced reinforcement methods was proposed to insure stable gateroad ahead of mining. Methane drainage and nitrogen injection were implemented to eliminate hazards associated with mine fire and spontaneous combustion. Since the development of gateroad has just completed,and retreat mining has not begun,the effectiveness of the proposed methods is unknown at this point. However,monitoring will continue until after mining.The results will be published in a separate paper.
基金funded by the National Natural Science Foundation of China(No.51374201,51323004)the State Key Development Program for Basic Research of China(No.2013CB227900)the College Student’s Program for Innovation of China University of Mining and Technology of China(No.201507)
文摘A mechanical model to control the top-coal deformation is established in accordance with the structural characters of the gob-side entry surrounding rock for the fully-mechanic top-coal caving; the analytical solution of top coal roof-sag curve is deduced with Winkler elastic foundation beam model. By means of a calculating and analytic program, the top coal roof-sag values are calculated under the conditions of different supporting intensities, widths of narrow pillars and stiffness of top coal; meanwhile, the relationship between the roof-sag values and supporting intensity, width of narrow pillars and stiffness of top coal is analyzed as well. With the actual situation of the gob-side entry taken into consideration, the parameters of top-coal control are determined and a supporting plan is proposed for the top-coal control,which is proved to be reliable and effective by on-site verification. Some theoretical guidance and advice are put forward for the top-coal deformation control in gob-side entry for fully mechanized top-coal caving face.